1.3 Construction schedule
1.3.1 Calculate working consumptions
Calculate the working consumptions according to the engineering quantities and labor quotas.
Labor quotas are shown in Table- 2. Labor consumption calculation is shown in Table- 6, and Table- 7.
Itemized project | units | Labor productivity standards |
Column steel bar | Workday /t | 2.86 |
Beam steel bar | Workday / t | 3.09 |
Second-beam steel bar | Workday / t | 3.70 |
slab steel bar | Workday / t | 3.03 |
Workday/10m² | 1.59 | |
Beam formwork | Workday/10m² | 1.38 |
Second-beam formwork | Workday/10m² | 1.62 |
slab formwork | Workday/10m² | 1.10 |
Workday /m3 | 1.08 | |
Beam concrete | Workday/ m3 | 0.55 |
Second-beam concrete | Workday / m3 | 0.55 |
slab concrete | Workday / m3 | 0.56 |
Column formwork dismantle | Workday /10m2 | 0.68 |
Beam formwork dismantle | Workday /10m2 | 0.59 |
Second-beam formwork dismantle | Workday /10m2 | 0.70 |
slab formwork dismantle | Workday /10m2 | 0.473 |
1.3.2 Construction duration
According to the number of each construction team and daily work shift, calculate the construction duration as shown in Table- 6 and Table- 7.
1.3.3 Construction schedule
Draw the horizontal chart of the flow construction schedule as shown in Table- 8, and Table- 9.
Draw the labor forces dynamic diagram.
The formwork professional team should be as continuous as possible.