Construction schedule

1.3 Construction schedule

1.3.1 Calculate working consumptions

Calculate the working consumptions according to the engineering quantities and labor quotas.

Labor quotas are shown in Table- 2. Labor consumption calculation is shown in Table- 6, and Table- 7.

Table- 2 Labor quotas

Itemized project

units

Labor productivity standards

Column steel bar

Workday /t

2.86

Beam  steel bar

Workday / t

3.09

Second-beam steel bar

Workday / t

3.70

slab steel bar

Workday / t

3.03

Column formwork

Workday/10m²

1.59

Beam formwork

Workday/10m²

1.38

Second-beam formwork

Workday/10m²

1.62

slab formwork

Workday/10m²

1.10

Column concrete

Workday /m3

1.08

Beam concrete

Workday/ m3

0.55

Second-beam concrete

Workday / m3

0.55

slab concrete

Workday / m3

0.56

Column formwork dismantle

Workday /10m2

0.68

Beam formwork dismantle

Workday /10m2

0.59

Second-beam formwork dismantle

Workday /10m2

0.70

slab formwork dismantle

Workday /10m2

0.473

 

1.3.2 Construction duration

According to the number of each construction team and daily work shift, calculate the construction duration as shown in Table- 6 and Table- 7.

1.3.3 Construction schedule

Draw the horizontal chart of the flow construction schedule as shown in Table- 8, and Table- 9.

Draw the labor forces dynamic diagram.

The formwork professional team should be as continuous as possible.