  • 1 Contents of Module Design
    • 1.1 Task book
    • 1.2 Construction scheme
    • 1.3 Construction schedule
    • 1.4 Construction Site Layout
    • 1.5 Main technical and organization measures
  • 2 Drawing contents
    • 2.1 contents
  • 3 Reference data in Module Design
    • 3.1 contents
contents

In a labor force organization, the number of professional teams can be up-regulated or down-regulated, but once determined, no changes are allowed.

Estimation of 1m³ concrete materials consumption: Cement-320kg, sands-0.49 m3, stones-0.926 m3. Material stacking quota: cement-1.4t/m2, sands-1.6 m3/ m2, stones-1.6 m3/ m2. Other reference data are shown in Table- 3.

Table- 3 Other reference data

Labor forces organization

Other materials and machinery

Temporary roads, working houses

Professional team

Team number

Name

Standard

Name

Standard

Note

Formwork team

25~35

Stirring machine

20 m2 each

One way road

3.5m width


Steel bar team

9~18

Wooden work shed

60 m2 each

Two-way roads

6.0m width


Concrete team

15~25

Formwork yard

100 m2

Office room

15~20 m2

By requirements



Steel working shed

200~300m2

Conference room

30~40 m2




Steel raw materials and semi-finished products stacking site

200 m2

Guardhouse

8~10m2




formwork material stacking site

100 m2

Small tools library

15~20m2






Common used Materials library

15~20m2






Workers dormitory

15~20 m2, 8~10 per room

By requirements





Workers kitchen

30~40 m2






Shower room

20~30m2






Toilet

20~30 m2