In a labor force organization, the number of professional teams can be up-regulated or down-regulated, but once determined, no changes are allowed.
Estimation of 1m³ concrete materials consumption: Cement-320kg, sands-0.49 m3, stones-0.926 m3. Material stacking quota: cement-1.4t/m2, sands-1.6 m3/ m2, stones-1.6 m3/ m2. Other reference data are shown in Table- 3.
Labor forces organization | Other materials and machinery | Temporary roads, working houses | ||||
Professional team | Team number | Name | Standard | Name | Standard | Note |
Formwork team | 25~35 | Stirring machine | 20 m2 each | One way road | 3.5m width | |
Steel bar team | 9~18 | Wooden work shed | 60 m2 each | Two-way roads | 6.0m width | |
Concrete team | 15~25 | Formwork yard | 100 m2 | Office room | 15~20 m2 | By requirements |
Steel working shed | 200~300m2 | Conference room | 30~40 m2 | |||
Steel raw materials and semi-finished products stacking site | 200 m2 | Guardhouse | 8~10m2 | |||
formwork material stacking site | 100 m2 | Small tools library | 15~20m2 | |||
Common used Materials library | 15~20m2 | |||||
Workers dormitory | 15~20 m2, 8~10 per room | By requirements | ||||
Workers kitchen | 30~40 m2 | |||||
Shower room | 20~30m2 | |||||
Toilet | 20~30 m2 | |||||